SPP-GEN-2024-282
150 MW generation in Meade, SD · In queue since March 2025
150 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-282 is a proposed solar generation project located in Meade County, South Dakota. The project, with a total capacity of 150 MW, is interconnected to the Southwest Power Pool (SPP) via the Maurine - New Underwood 230 kV Line. The designated utility is WAPA, and the service type is Energy Resource/Network Resource (ER/NR).
The project entered the SPP interconnection queue on March 1, 2025, and is currently listed as active. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
SD
County
Meade
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WAPA
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Maurine - New Underwood 230 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.