SPP-GEN-2024-283
150 MW generation in Meade, SD · In queue since March 2025
150 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-283 is a proposed 150 MW solar generation project located in Meade County, South Dakota. The project is in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The designated point of interconnection (POI) is the Maurine - New Underwood 230 kV Line, and the requested service type is ER/NR. The interconnecting utility is Western Area Power Administration (WAPA).
Generated from interconnection queue and public data sources
State
SD
County
Meade
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WAPA
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Maurine - New Underwood 230 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-283