Project SPP-GEN-2024-283 — Project Summary

Queue ID
SPP-GEN-2024-283
Capacity
150 MW
Technology
Solar
Status
active
Location
Meade, SD
Region
SPP
Developer
IA Status

SPP-GEN-2024-283

SPP-GEN-2024-283BetaActiveSolar / PhotovoltaicSPPLive · SPP

150 MW generation in Meade, SD · In queue since March 2025

150 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-283 is a proposed 150 MW solar generation project located in Meade County, South Dakota. The project is in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The designated point of interconnection (POI) is the Maurine - New Underwood 230 kV Line, and the requested service type is ER/NR. The interconnecting utility is Western Area Power Administration (WAPA).

Generated from interconnection queue and public data sources

Project Details

State

SD

County

Meade

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

WAPA

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Maurine - New Underwood 230 kV Line

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-GEN-2024-283