199.8 MW generation in Crawford, KS · In queue since March 2025
199.8 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-287 is a proposed solar generation project located in Crawford County, Kansas, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 199.8 MW, is slated to interconnect to the Wolf Creek - Blackberry 345 kV Line. The queue entry date is March 1, 2025.
The project is currently listed as active in the SPP interconnection queue, under the service type ER/NR. The utility associated with the project is NEETSW.
Generated from interconnection queue and public data sources
State
KS
County
Crawford
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NEETSW
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Wolf Creek - Blackberry 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.