SPP-GEN-2024-288
130 MW generation in Cloud, KS · In queue since March 2025
130 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-288 is a proposed 130 MW solar generation project located in Cloud County, Kansas. The project is in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the Elm Creek - Tobias 345 kV Line. The project's service type is Energy Resource/Network Resource (ER/NR).
The project is listed as "active" in the SPP queue. The developer is not specified in the queue data. The interconnecting utility is Sunflower Electric Power Corporation (SUNC).
Generated from interconnection queue and public data sources
State
KS
County
Cloud
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Elm Creek - Tobias 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.