SPP-GEN-2024-295
115 MW storage in Eddy, NM · In queue since March 2025
115 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-295 is a proposed 115 MW battery storage project located in Eddy County, New Mexico. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of March 1, 2025. The proposed point of interconnection is the S Loving 115 kV Substation.
The project's service type is listed as ER/NR, and it is currently in active status within the SPP queue. The utility associated with the project is SPS.
Generated from interconnection queue and public data sources
State
NM
County
Eddy
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ER/NR
Point of Interconnection
S Loving 115 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Loving Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.