SPP-GEN-2024-298
167 MW generation in McIntosh, OK · In queue since March 2025
167 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-298 is a proposed solar generation project with a total capacity of 167 MW. The project is located in McIntosh County, Oklahoma, and is interconnected within the Southwest Power Pool (SPP) queue. The proposed point of interconnection (POI) is the Muskogee - Pittsburg 345 kV Line.
The project entered the SPP interconnection queue on March 1, 2025. It is currently listed as "active" in the queue and is seeking ER/NR service type. Oklahoma Gas & Electric (OGE) is listed as the utility.
Generated from interconnection queue and public data sources
State
OK
County
McIntosh
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Muskogee - Pittsburg 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.