SPP-GEN-2024-308
199 MW generation in Woodward, OK · In queue since March 2025
199 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-308 is a proposed 199 MW wind and battery hybrid project located in Woodward County, Oklahoma. The project is listed in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The interconnecting utility is Western Farmers Electric Cooperative (WFEC).
The project's point of interconnection (POI) is the Okeene - Mooreland 138 kV line. The requested service type is Energy Resource/Network Resource (ER/NR). As of the latest data, the project's interconnection status is listed as active.
Generated from interconnection queue and public data sources
State
OK
County
Woodward
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Okeene - Mooreland 138 kV line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WFEC_MOORELAND_2
- POI Substation
- Mooreland
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-308