SPP-GEN-2024-318
199 MW storage in Tulsa, OK · In queue since March 2025
199 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-318 is a proposed 199 MW battery storage project in Tulsa County, Oklahoma. The project is located within the Southwest Power Pool (SPP) service area and is interconnected to the Tulsa North - American Airlines 138 kV Line. The queue entry date is March 1, 2025.
The project, which is listed as active in the SPP interconnection queue, is pursuing Energy Resource and Network Resource service. The utility is listed as AEP.
Generated from interconnection queue and public data sources
State
OK
County
Tulsa
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Tulsa North - American Airlines 138 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.