Project SPP-GEN-2024-322 — Project Summary

Queue ID
SPP-GEN-2024-322
Capacity
75 MW
Technology
Battery
Status
active
Location
Graham, KS
Region
SPP
Developer
IA Status

SPP-GEN-2024-322

SPP-GEN-2024-322BetaActiveBattery/Storage / BatterySPPLive · SPP

75 MW storage in Graham, KS · In queue since March 2025

75 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-322 is a proposed 75 MW battery storage project located in Graham County, Kansas. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The designated point of interconnection (POI) is the Redlin - Beach3 115 kV line.

The project, categorized as energy resource and network resource (ER/NR) service type, is currently active in the SPP queue. The utility associated with the project is MIDW.

Generated from interconnection queue and public data sources

Project Details

State

KS

County

Graham

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

MIDW

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Redlin - Beach3 115 kV line

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-GEN-2024-322