SPP-GEN-2024-326
225 MW storage in Stark, ND · In queue since March 2025
225 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-326 is a proposed 225 MW battery storage project located in Stark County, North Dakota. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The designated point of interconnection (POI) is the Belfield 230 kV Substation. The project's service type is listed as ER/NR.
The project is currently listed as active in the SPP queue. WAPA is the utility associated with the project.
Generated from interconnection queue and public data sources
State
ND
County
Stark
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WAPA
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Belfield 230 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Belfield Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.