SPP-GEN-2024-327
200 MW storage in Ward, ND · In queue since March 2025
200 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-327 is a proposed 200 MW battery storage project located in Ward County, North Dakota. The project is listed in the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-GEN-2024-327, with a queue entry date of March 1, 2025. The designated point of interconnection (POI) is the Berthold 115 kV Substation. The project's listed service type is ER/NR.
The developer is not specified in the data, but the utility is listed as CPEC. The project is currently listed as active in the SPP queue. A proposed commercial operation date and interconnection agreement (IA) status are not available in the provided data. Recent news coverage of the project is not indicated.
Generated from interconnection queue and public data sources
State
ND
County
Ward
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
CPEC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Berthold 115 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WAUE_NSP_BERTHOLD
- POI Substation
- Berthold Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.