Project SPP-GEN-2024-330 — Project Summary

Queue ID
SPP-GEN-2024-330
Capacity
225 MW
Technology
Battery
Status
active
Location
Butler, KS
Region
SPP
Developer
IA Status

SPP-GEN-2024-330

SPP-GEN-2024-330BetaActiveBattery/Storage / BatterySPPLive · SPP

225 MW storage in Butler, KS · In queue since March 2025

225 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-330 is a proposed 225 MW battery storage project located in Butler County, Kansas. The project, which interconnects to the Midian 138 kV Substation, is in the Southwest Power Pool (SPP) interconnection queue as of March 1, 2025. The project's service type is Energy Resource/Network Resource (ER/NR).

The development project is listed as active in the SPP queue. The designated utility is Western Resources (WERE).

Generated from interconnection queue and public data sources

Project Details

State

KS

County

Butler

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

WERE

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Midian 138 kV Substation

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
HIGH
POI Substation
Midian Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-GEN-2024-330