SPP-GEN-2024-334
124 MW generation in Kay, OK · In queue since March 2025
124 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-334 is a proposed 124 MW gas-fired generation project located in Kay County, Oklahoma. The project is listed in the Southwest Power Pool (SPP) interconnection queue, with an entry date of March 1, 2025. The designated point of interconnection (POI) is the Ranch Road 345 kV Substation. OG&E is the interconnecting utility.
The project's service type is listed as ER/NR, and it is currently in active status within the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Kay
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Ranch Road 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Ranch Road 12 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-334