Project SPP-GEN-2024-338 — Project Summary

Queue ID
SPP-GEN-2024-338
Capacity
350 MW
Technology
Solar
Status
active
Location
Johnston, OK
Region
SPP
Developer
IA Status

SPP-GEN-2024-338

SPP-GEN-2024-338BetaActiveSolar / PhotovoltaicSPPLive · SPP

350 MW generation in Johnston, OK · In queue since March 2025

350 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-338 is a proposed 350 MW solar generation project in Johnston County, Oklahoma. The project is located within the Southwest Power Pool (SPP) region and is listed in the SPP interconnection queue as of March 1, 2025. The proposed point of interconnection (POI) is the Pittsburg - Johnston County 345 kV line.

The project, which utilizes photovoltaic technology, is seeking ER/NR service and is currently listed as active in the queue. The interconnecting utility is AEP.

Generated from interconnection queue and public data sources

Project Details

State

OK

County

Johnston

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Pittsburg - Johnston County 345 kV line

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP South Hub
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-GEN-2024-338