SPP-GEN-2024-343
470.5 MW generation in Harrison, TX · In queue since March 2025
470.5 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-343 is a proposed 470.5 MW gas-fired generation project located in Harrison County, Texas. The project is listed in the Southwest Power Pool (SPP) interconnection queue, with an entry date of March 1, 2025. The point of interconnection is the LeBrock 345 kV Substation, and the requested service type is ER/NR. The interconnecting utility is AEP.
The project is currently listed as active in the SPP queue. The technology detail specifies "Thermal / Gas". No information is available regarding a proposed commercial operation date, interconnection agreement status, developer, or if the project is linked to an existing operating plant. There is no indication of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Harrison
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
LeBrock 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.