SPP-GEN-2024-345
600 MW generation in Nowata, OK · In queue since March 2025
600 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-345 is a proposed 600 MW wind generation project located in Nowata County, Oklahoma. The project is listed in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the Delaware 345 kV Substation. The project's requested service type is Energy Resource/Network Resource (ER/NR).
The project is currently listed as active in the SPP queue. American Electric Power (AEP) is the utility associated with the interconnection. There is recent news coverage of this project.
Generated from interconnection queue and public data sources
State
OK
County
Nowata
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Delaware 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Delaware Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-345