SPP-GEN-2024-352
199 MW storage in Jackson, MO · In queue since March 2025
199 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-352 is a proposed 199 MW battery storage project located in Jackson County, Missouri. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The interconnecting utility is Western Energy Resources (WERE).
The project's point of interconnection (POI) is the Sibley 345 kV Substation. The service type requested for the project is Energy Resource/Network Resource (ER/NR). As of the latest data, the project remains in active status within the SPP queue.
Generated from interconnection queue and public data sources
State
MO
County
Jackson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Sibley 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Sibley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.