SPP-GEN-2024-361
80 MW generation in Lincoln, OK · In queue since March 2025
80 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-361 is a proposed 80 MW solar and battery hybrid project located in Lincoln County, Oklahoma. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the Spring Valley - Warwick 138 kV line, and the requested service type is ER/NR.
The project is currently listed as active in the SPP queue. Oklahoma Gas & Electric (OGE) is the utility associated with the interconnection.
Generated from interconnection queue and public data sources
State
OK
County
Lincoln
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Spring Valley - Warwick 138 kV line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Warwick
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-361