SPP-GEN-2024-362
140 MW generation in Grady, OK · In queue since March 2025
140 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-362 is a proposed 140 MW solar and battery energy storage hybrid project located in Grady County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on March 1, 2025. The proposed point of interconnection is the Leonard 138 kV Substation. The project's service type is Energy Resource/Network Resource (ER/NR).
The development project is listed as active in the SPP queue. The project is a hybrid facility consisting of both solar photovoltaic generation and battery energy storage, but the individual capacities of each component are not specified. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
OK
County
Grady
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Leonard 138 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-362