SPP-GEN-2024-368
250 MW storage in Gray, TX · In queue since March 2025
250 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-368 is a proposed 250 MW battery storage project located in Gray County, Texas. The project is interconnected within the Southwest Power Pool (SPP) queue, with a queue entry date of March 1, 2025. The proposed service type is Energy Resource/Network Resource (ER/NR). The point of interconnection (POI) is the Bowers 115 kV Substation, served by utility SPS.
The project is currently listed as active in the SPP interconnection queue. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
TX
County
Gray
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Bowers 115 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Bowers Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.