SPP-GEN-2024-373
120 MW generation in Choctaw, OK · In queue since March 2025
120 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-373 is a proposed 120 MW solar and battery hybrid project located in Choctaw County, Oklahoma. The project is listed in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on March 1, 2025. The interconnecting utility is Western Farmers Electric Cooperative (WFEC).
The project consists of both solar photovoltaic generation and battery energy storage, though the individual capacities of each component are not specified. The proposed point of interconnection (POI) is the Unger - West Bank Tap 138 kV Line. The project is currently listed as active in the SPP queue and is seeking Energy Resource (ER) and Network Resource (NR) service types.
Generated from interconnection queue and public data sources
State
OK
County
Choctaw
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Unger - West Bank Tap 138 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.