Project SPP-GEN-2024-377 — Project Summary

Queue ID
SPP-GEN-2024-377
Capacity
1350 MW
Technology
Gas
Status
active
Location
Harrison, TX
Region
SPP
Developer
IA Status

SPP-GEN-2024-377

SPP-GEN-2024-377BetaActiveThermal / GasSPPLive · SPP

1,350 MW generation in Harrison, TX · In queue since March 2025

1,350 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-377 is a proposed 1350 MW gas-fired generation project located in Harrison County, Texas. The project is listed in the Southwest Power Pool (SPP) interconnection queue, with an entry date of March 1, 2025. The proposed point of interconnection (POI) is the Pirkey 345 kV Substation. The project's service type is listed as ER/NR.

The project is currently listed as active in the SPP queue. American Electric Power (AEP) is listed as the interconnecting utility.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Harrison

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Pirkey 345 kV Substation

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP South Hub
Hub Confidence
HIGH
POI Substation
Pirkey Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.