SPP-GEN-2024-379
1,350 MW generation in Bossier Parish, LA · In queue since March 2025
1,350 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-379 is a proposed 1350 MW gas-fired generation project located in Bossier Parish, Louisiana. The project is listed in the Southwest Power Pool (SPP) interconnection queue, with an entry date of March 1, 2025. The designated point of interconnection (POI) is the Longwood - El Dorado 345 kV Line. American Electric Power (AEP) is listed as the utility.
The project's proposed service type is Energy Resource/Network Resource (ER/NR). As of the latest data, the project's status in the SPP queue is "active." The proposed project has appeared in recent news.
Generated from interconnection queue and public data sources
State
LA
County
Bossier Parish
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Longwood - El Dorado 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.