SPP-GEN-2024-SR8
70 MW storage in Greeley, NE · In queue since April 2024 · Proposed COD December 2026
70 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
SPP-GEN-2024-SR8 is a proposed 70 MW battery storage project in Greeley County, Nebraska. The project, which consists of 70 MW of battery capacity, is interconnected to the Southwest Power Pool (SPP) via the Spalding to North Loup 115kV point of interconnection. The queue entry date is April 3, 2024, with a proposed commercial operation date of December 31, 2026. The project's interconnection status is currently in the Facility Study phase.
The project is being developed within the Nebraska Public Power District (NPPD) service area. The project is currently listed as active within the SPP interconnection queue.
Generated from interconnection queue and public data sources
State
NE
County
Greeley
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
—
Point of Interconnection
Spalding to North Loup 115kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-SR8