Project SPP-GEN-2025-GR2 — Project Summary

Queue ID
SPP-GEN-2025-GR2
Capacity
120 MW
Technology
Wind
Status
active
Location
Elida, NM
Region
SPP
Developer
IA Status

SPP-GEN-2025-GR2

SPP-GEN-2025-GR2BetaActiveWindSPPLive · SPP

120 MW generation in Elida, NM · In queue since June 2025

120 MW

Capacity

0

Components

11 months

In Queue

IA Status

Interconnection

Total Duration

11 months

Pre-Study0%
Queue EntryJun 30, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2025-GR2 is a proposed 120 MW wind generation project located in Elida County, New Mexico. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on June 30, 2025. The interconnecting utility is Southwestern Public Service (SPS).

The project's point of interconnection (POI) is the San Juan Mesa 230 kV Substation. The service type requested is Energy Resource (ER). The project's status in the SPP queue is currently listed as active.

Generated from interconnection queue and public data sources

Project Details

State

NM

County

Elida

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

SPS

Entity

SPP

Service Type

ER

Point of Interconnection

San Juan Mesa 230 kV Substation

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP South Hub
Hub Confidence
HIGH
Nearest Node (Estimated)
SPS.SJUANWIND1
POI Substation
San Juan Tap

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-GEN-2025-GR2