SPP-GEN-2025-SR21
100 MW generation in Tulsa, OK · In queue since June 2025
100 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
Total Duration
11 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2025-SR21 is a proposed 100 MW gas-fired generation project located in Tulsa County, Oklahoma. The project, which utilizes thermal technology, is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of June 12, 2025. The point of interconnection is the Tulsa Power Station 138kV Substation. The interconnecting utility is AEP.
The project's service type is Energy Resource. It is currently listed as active in the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Tulsa
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER
Point of Interconnection
Tulsa Power Station 138kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KACYQUIND1UNGT2
- POI Substation
- Quindaro Power Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2025-SR21