SPP-GEN-2025-SR25
200 MW generation in Sperry, OK · In queue since June 2025
200 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
Total Duration
11 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2025-SR25 is a proposed 200 MW gas-fired generation project located in Sperry County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of June 12, 2025. The point of interconnection is the Tulsa North 138kV Substation. The project's service type is Energy Resource (ER).
The project is listed as active in the SPP queue. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
OK
County
Sperry
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER
Point of Interconnection
Tulsa North 138kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Tulsa North #2 Substation