SPP-GEN-2025-SR31
170 MW storage in Meadow Grove, NE · In queue since November 2025
170 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
Total Duration
6 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2025-SR31 is a proposed 170 MW battery storage project located in Meadow Grove County, Nebraska. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on November 7, 2025. The designated utility is NPPD, and the point of interconnection is the Antelope(640520) - Hoskins(640226) 345kV line. The project's service type is Energy Resource (ER).
The development project is currently listed as active within the SPP queue.
Generated from interconnection queue and public data sources
State
NE
County
Meadow Grove
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
ER
Point of Interconnection
Antelope(640520) - Hoskins(640226) 345kV
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2025-SR31