SPP-GEN-2026-PR1
52.63 MW generation in Garfield County, TX · In queue since December 2025
52.63 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Total Duration
5 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2026-PR1 is a proposed wind generation project with a total capacity of 52.63 MW. The project is located in Garfield County, Texas, and is interconnected within the Southwest Power Pool (SPP) region. OG&E is listed as the utility.
The project entered the SPP interconnection queue on December 1, 2025. Its interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
State
TX
County
Garfield County
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OG&E
Entity
SPP
Service Type
ER
Point of Interconnection
Beaver County 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Beaver County Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2026-PR1