SPP-GEN-2026-PR5
60.4 MW storage in Goultry, OK · In queue since January 2026
60.4 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
Total Duration
4 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2026-PR5 is a proposed 60.4 MW battery storage project located in Goultry County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on January 7, 2026. OG&E is the utility associated with the project. The point of interconnection is the Woodring 345kV Substation.
The project's service type is listed as Energy Resource (ER). As of the latest data, the project remains in active status within the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Goultry
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OG&E
Entity
SPP
Service Type
ER
Point of Interconnection
Woodring 345kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- OKGE.WFEC.SKLCRKSLR
- POI Substation
- Woodring Substation