SPP-GEN-2026-SR15
200 MW storage in Balko, OK · In queue since January 2026
200 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
Total Duration
4 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2026-SR15 is a proposed 200 MW battery storage project located in Balko County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on January 19, 2026. The interconnecting utility is Oklahoma Gas & Electric (OGE).
The project's point of interconnection (POI) is the Beaver County - Woodward EHV Double Circuit (Badger) 345kV line. The designated service type for the project is Energy Resource (ER). As of the latest data, the project is listed as active in the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Balko
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
ER
Point of Interconnection
Beaver County - Woodward EHV Dbl Ckt (Badger) 345kV
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Woodward
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.