SRP_ANPP-ANPP HVS-Q22
125 MW generation in Maricopa, AZ · In queue since February 2016 · Proposed COD December 2025
125 MW
Capacity
1
Components
Solar
10y 3m
In Queue
—
IA Status
COD target: 2025
Total Duration
9y 10m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
SRP_ANPP-ANPP HVS-Q22 is a proposed solar generation project with a total capacity of 125 MW, located in Maricopa County, Arizona. The project is in the Salt River Project interconnection queue, with an entry date of February 11, 2016, and a proposed commercial operation date of December 31, 2025.
The development project, located in the Western region, consists of 125 MW of solar capacity. It is listed as active in the interconnection queue of Salt River Project, under the entity SRP_ANPP.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP_ANPP
Service Type
—
Point of Interconnection
Hassayampa 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN