SRP_ANPP-ANPP HVS-Q38
800 MW hybrid in Maricopa, AZ · In queue since February 2023 · Proposed COD June 2027
800 MW
Capacity
1
Components
Solar
3y 3m
In Queue
—
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
SRP_ANPP-ANPP HVS-Q38 is a proposed 800 MW hybrid solar and battery project located in Maricopa County, Arizona. The development project consists of 800 MW of solar capacity. It is in the Salt River Project interconnection queue, with an entry date of February 8, 2023, and a proposed commercial operation date of June 1, 2027.
The project is interconnected at the Hassayampa 500 kV point of interconnection. The developer is listed as SRP_ANPP. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP_ANPP
Service Type
—
Point of Interconnection
Hassayampa 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.