SRP_ANPP-ANPP HVS-Q40
425 MW generation in Maricopa, AZ · In queue since August 2023 · Proposed COD June 2028
425 MW
Capacity
1
Components
Gas
2y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
SRP_ANPP-ANPP HVS-Q40 is a proposed 425 MW gas-fired generation project located in Maricopa County, Arizona. The project is being developed by SRP_ANPP and is interconnected within the Salt River Project queue. It entered the queue on August 18, 2023, with a proposed commercial operation date of June 1, 2028.
The project will connect to the grid at the Hassayampa 500 kV point of interconnection. As of the latest data, the project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP_ANPP
Service Type
—
Point of Interconnection
Hassayampa 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.