SRP-Cluster 24-Q2402
300 MW hybrid in Maricopa, AZ · In queue since February 2024 · Proposed COD December 2028
300 MW
Capacity
1
Components
Solar
2y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
SRP-Cluster 24-Q2402 is a proposed 300 MW solar and battery hybrid project located in Maricopa County, Arizona. The project, which is in the West region, consists of 300 MW of solar capacity. It is being developed within the Salt River Project (SRP) utility territory.
The project is currently active in the SRP interconnection queue, with an entry date of February 5, 2024, and a proposed commercial operation date of December 31, 2028. The point of interconnection is the Hassayampa 500 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP
Service Type
—
Point of Interconnection
Hassayampa 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SRP-Cluster 24-Q2402