SRP-Cluster 24-Q2403
398.14 MW generation in Maricopa, AZ · In queue since February 2024 · Proposed COD April 2028
398.14 MW
Capacity
1
Components
Gas
2y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
SRP-Cluster 24-Q2403 is a proposed 398.14 MW gas-fired generation project located in Maricopa County, Arizona. The project is being developed within the Salt River Project (SRP) service area. It entered the SRP interconnection queue on February 5, 2024, with a proposed commercial operation date of April 1, 2028.
The project, which consists of 398.14 MW of gas-fired capacity, is currently listed as active in the interconnection queue. The point of interconnection (POI) is the Hassayampa 500 kV substation. The project has appeared in recent news coverage regarding power projects in the region.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP
Service Type
—
Point of Interconnection
Hassayampa 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.