SRP-Cluster 24-Q2410
301.325 MW hybrid in Pinal, AZ · In queue since February 2024 · Proposed COD September 2027
301.325 MW
Capacity
1
Components
Solar
2y 3m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-30
SRP-Cluster 24-Q2410 is a proposed 301.32 MW hybrid solar and battery project located in Pinal County, Arizona. The development project, under the utility Salt River Project (SRP), consists of 301.32 MW of solar capacity. It is currently active in the SRP interconnection queue, with an entry date of February 5, 2024, and a proposed commercial operation date of September 30, 2027. The point of interconnection is Pinal West 500 kV.
The project is located in the Western region of the United States. As of the latest data, no interconnection agreement (IA) status is available. The developer entity is listed as SRP. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP
Service Type
—
Point of Interconnection
Pinal West 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.