SRP-Cluster 24-Q2412
822.12 MW hybrid in Navajo, AZ · In queue since February 2024 · Proposed COD December 2028
822.12 MW
Capacity
1
Components
Solar
2y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-30
SRP-Cluster 24-Q2412 is a proposed 822.12 MW hybrid solar and battery energy project located in Navajo County, Arizona. The project consists of 822.12 MW of solar capacity. It is listed in the Salt River Project (SRP) interconnection queue, with an entry date of February 5, 2024, and a proposed commercial operation date of December 30, 2028. The point of interconnection is the Silver King-Coronado 500 kV Line.
The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP
Service Type
—
Point of Interconnection
Silver King-Coronado 500 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.