SRP_PV-PC-PV-PC-Q09
400 MW hybrid in Pinal, AZ · In queue since September 2018 · Proposed COD December 2023
400 MW
Capacity
1
Components
Solar
7y 8m
In Queue
—
IA Status
COD target: 2023
Total Duration
5y 3m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
SRP_PV-PC-PV-PC-Q09 is a proposed 400 MW hybrid solar and battery energy storage project located in Pinal County, Arizona. The development project, with Salt River Project as the utility, consists of 400 MW of solar photovoltaic generation.
The project is currently active in the Salt River Project interconnection queue, with an original queue entry date of September 12, 2018. The proposed commercial operation date is December 31, 2023. The point of interconnection is at the Pinal Central 230 kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP_PV-PC
Service Type
—
Point of Interconnection
Pinal Central 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SRP_PV-PC-PV-PC-Q09