SRP-SRP-Q64
17 MW generation in Pinal, AZ · In queue since June 2020 · Proposed COD December 2020
17 MW
Capacity
1
Components
Gas
5y 11m
In Queue
—
IA Status
COD target: 2020
Total Duration
6 months
Schedule
66 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-12-01
SRP-SRP-Q64 is a proposed 17 MW gas-fired generation project located in Pinal County, Arizona. The project is listed in the Salt River Project interconnection queue with a queue entry date of June 19, 2020. The listed point of interconnection is Desert Basin 230 kV.
The proposed commercial operation date for this development project is December 1, 2020. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP
Service Type
—
Point of Interconnection
Desert Basin 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SRP-SRP-Q64