Project SRP-SRP-Q76 — Project Summary

Queue ID
SRP-SRP-Q76
Capacity
332 MW
Technology
Gas
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status

SRP-SRP-Q76

SRP-SRP-Q76BetaActiveGasSRPLBNL

332 MW generation in Pinal, AZ · In queue since May 2021 · Proposed COD June 2026

332 MW

Capacity

1

Components

Gas

5 years

In Queue

IA Status

COD target: 2026

Interconnection

Total Duration

5y 1m

Pre-Study0%
Queue EntryMay 6, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

About

SRP-SRP-Q76 is a proposed 332 MW gas-fired generation project located in Pinal County, Arizona. The project is being developed within the Salt River Project (SRP) service territory. It entered the SRP interconnection queue on May 6, 2021, with a proposed commercial operation date of June 1, 2026. The point of interconnection is the Pinal Central-Browning 500 kV Line.

The project consists of 332 MW of gas-fired generation capacity. As of the latest data, the project remains active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Pinal

Grid Region

Mountain West

Market

Developer

Utility

Salt River Project

Entity

SRP

Service Type

Point of Interconnection

Pinal Central-Browning 500 kV Line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.