SRP-SRP-Q81
30 MW generation in Maricopa, AZ · In queue since June 2021 · Proposed COD February 2025
30 MW
Capacity
1
Components
Gas
4y 11m
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 8m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-02-01
SRP-SRP-Q81 is a proposed 30 MW gas-fired generation project located in Maricopa County, Arizona. The project is in the Salt River Project (SRP) interconnection queue, with an entry date of June 3, 2021. The proposed commercial operation date is February 1, 2025.
The project, sponsored by SRP, consists of 30 MW of gas-fired capacity and is currently listed as active in the interconnection queue. The point of interconnection is the Kyrene 69 kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Salt River Project
Entity
SRP
Service Type
—
Point of Interconnection
Kyrene 69 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SRP-SRP-Q81