TEC-100
21 MW hybrid in Polk, FL · In queue since March 2023 · Proposed COD April 2024
21 MW
Capacity
1
Components
Gas
3y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
1y 1m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-01
TEC-100 is a proposed 21 MW hybrid development project located in Polk County, Florida. The project, under development by Tampa Electric Company (TEC), consists of a 21 MW gas-fired generation component. It is listed in the queue of an unspecified ISO/RTO with a queue entry date of March 13, 2023, and a proposed commercial operation date of April 1, 2024. The project's interconnection status is currently in the Cluster Study phase.
The proposed project is designated as a hybrid due to its technology detail listing both Gas and Coal. The point of interconnection (POI) is the Polk Substation in Polk County. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
FL
County
Polk
Grid Region
Southeast
Market
—
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Service Type
—
Point of Interconnection
Polk Substation, Polk County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEC-100