TEC-106
74.5 MW generation in Hillsborough, FL · In queue since June 2023 · Proposed COD December 2025
74.5 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 6m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
TEC-106 is a proposed solar generation project located in Hillsborough County, Florida, within the Southeast region. The project, with a total capacity of 74.5 MW, is being developed by Tampa Electric Company (TEC). It consists of 74.5 MW of solar photovoltaic generation.
The project is currently in the Tampa Electric Company interconnection queue as entry TEC-106, with a queue entry date of June 15, 2023. The proposed commercial operation date is December 1, 2025. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is the Mines Substation in Hillsborough County.
Generated from interconnection queue and public data sources
State
FL
County
Hillsborough
Grid Region
Southeast
Market
—
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Service Type
—
Point of Interconnection
Mines Substation, Hillsborough County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEC-106