TEC-112
74.5 MW generation in Hillsborough, FL · In queue since March 2024 · Proposed COD December 2026
74.5 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
TEC-112 is a proposed solar generation project with a total capacity of 74.5 MW, located in Hillsborough County, Florida. The project is listed in the Tampa Electric Company (TEC) interconnection queue, with an entry date of March 31, 2024. Its proposed commercial operation date is December 1, 2026. The interconnection status is currently in the Cluster Study phase.
The project, sponsored by TEC, is planned to connect to the Sun City Substation in Hillsborough County. It is an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
FL
County
Hillsborough
Grid Region
Southeast
Market
—
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Service Type
—
Point of Interconnection
Sun City Substation, Hillsborough County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.