TEC-114
20 MW storage in Hillsborough, FL · In queue since October 2024 · Proposed COD December 2025
20 MW
Capacity
1
Components
Battery
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
1y 2m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
TEC-114 is a proposed 20 MW battery storage project located in Hillsborough County, Florida. The project, under development by Tampa Electric Company (TEC), entered the TEC interconnection queue on October 22, 2024, with a proposed commercial operation date of December 1, 2025. Its interconnection status is currently in the System Impact Study phase.
The project will interconnect at the Gannon Substation in Hillsborough County. As of the latest data, the project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
FL
County
Hillsborough
Grid Region
Southeast
Market
—
Developer
—
Utility
Tampa Electric Company
Entity
TEC
Service Type
—
Point of Interconnection
Gannon Substation, Hillsborough County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.