TEP-100
250 MW generation in Pima, AZ · In queue since October 2021 · Proposed COD May 2024
250 MW
Capacity
1
Components
Other
4y 7m
In Queue
—
IA Status
COD target: 2024
Total Duration
2y 7m
Schedule
24 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-01
TEP-100 is a proposed 250 MW generation project located in Pima County, Arizona. The project, under development by Tucson Electric Power Company (TEP), is categorized as "Other" technology. It consists of a single 250 MW component of "Other" type.
The project is listed in the utility's interconnection queue as of October 30, 2021, with a proposed commercial operation date of May 1, 2024. The point of interconnection is the North Loop 138kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
North Loop 138kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-100