Project TEP-100 — Project Summary

Queue ID
TEP-100
Capacity
250 MW
Technology
Other
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status

TEP-100

TEP-100BetaActiveOtherTEPLBNL

250 MW generation in Pima, AZ · In queue since October 2021 · Proposed COD May 2024

250 MW

Capacity

1

Components

Other

4y 7m

In Queue

IA Status

COD target: 2024

Interconnection

Total Duration

2y 7m

Schedule

24 months past proposed COD

Pre-Study0%
Queue EntryOct 30, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-01

About

TEP-100 is a proposed 250 MW generation project located in Pima County, Arizona. The project, under development by Tucson Electric Power Company (TEP), is categorized as "Other" technology. It consists of a single 250 MW component of "Other" type.

The project is listed in the utility's interconnection queue as of October 30, 2021, with a proposed commercial operation date of May 1, 2024. The point of interconnection is the North Loop 138kV Substation.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Pima

Grid Region

Mountain West

Market

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Service Type

Point of Interconnection

North Loop 138kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project TEP-100