TEP-103
768 MW generation in Apache, AZ · In queue since November 2021 · Proposed COD December 2024
768 MW
Capacity
1
Components
Other
4y 6m
In Queue
—
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
TEP-103 is a proposed 768 MW generation project located in Apache County, Arizona. The project, under development by Tucson Electric Power Company (TEP), utilizes an unspecified "Other" technology. It is interconnected to the Springerville 345kV Substation.
The project is currently active in the WestConnect interconnection queue, with an entry date of November 9, 2021. The proposed commercial operation date is December 31, 2024.
Generated from interconnection queue and public data sources
State
AZ
County
Apache
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Springerville 345kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN