TEP-106
320 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD December 2024
320 MW
Capacity
1
Components
Other
4y 5m
In Queue
—
IA Status
COD target: 2024
Total Duration
3 years
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
TEP-106 is a proposed 320 MW generation project located in Pima County, Arizona. The project, under development by Tucson Electric Power Company (TEP), utilizes an unspecified "Other" technology. It is listed as active in the utility's interconnection queue, with an entry date of December 8, 2021, and a proposed commercial operation date of December 31, 2024. The point of interconnection is the North Loop 138kV Substation.
The project consists of a single 320 MW component categorized as "Other". No interconnection agreement (IA) status is available for this project. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
North Loop 138kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-106