Project TEP-107 — Project Summary

Queue ID
TEP-107
Capacity
400 MW
Technology
Other
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status

TEP-107

TEP-107BetaActiveOtherTEPLBNL

400 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD December 2024

400 MW

Capacity

1

Components

Other

4y 5m

In Queue

IA Status

COD target: 2024

Interconnection

Total Duration

3 years

Schedule

16 months past proposed COD

Pre-Study0%
Queue EntryDec 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

About

TEP-107 is a proposed 400 MW generation project located in Pima County, Arizona. The project, under development by Tucson Electric Power Company (TEP), utilizes an unspecified "Other" technology. It is interconnected to the Tortolita 138kV point of interconnection.

The project is currently active in the Southwest Power Pool (SPP) interconnection queue, with an entry date of December 8, 2021. The proposed commercial operation date is December 31, 2024.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Pima

Grid Region

Mountain West

Market

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Service Type

Point of Interconnection

Tortolita 138kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project TEP-107