TEP-107
400 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD December 2024
400 MW
Capacity
1
Components
Other
4y 5m
In Queue
—
IA Status
COD target: 2024
Total Duration
3 years
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
TEP-107 is a proposed 400 MW generation project located in Pima County, Arizona. The project, under development by Tucson Electric Power Company (TEP), utilizes an unspecified "Other" technology. It is interconnected to the Tortolita 138kV point of interconnection.
The project is currently active in the Southwest Power Pool (SPP) interconnection queue, with an entry date of December 8, 2021. The proposed commercial operation date is December 31, 2024.
Generated from interconnection queue and public data sources
State
AZ
County
Pima
Grid Region
Mountain West
Market
—
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Service Type
—
Point of Interconnection
Tortolita 138kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TEP-107